Shetland Substation Works
Contracted to carry out works on anew substation on the mainland of Shetland over a 2 year programme. These works consist of the following activities:
- Provision of temporary haul road and hard standings.
- Installation of 28no direct buried, troughed or ducted 33kV cable circuits.
- Installation of 5no direct buried, troughed or ducted 132kV cable circuits.
- Installation of of a number of earth, LV and fibre cables.
- Fabrication and installation of 33kV switchroom cable support structures and other cable management.
- Duct proving and camera inspection of ducts installed by others prior to cable installation.
- Provision and installation of troughs associated with 8no 33kV and 132kV cable circuits.
- Installation of cleating and associated steelwork within 11no troughed cable routes.
- Installation of transition cable glands.
- Resin anchor installation and testing.
- Planning, procurement and delivery of required materials to the Shetland Isles.